Quick answer
A Justification and Approval is the written document agencies must prepare and have approved before awarding a contract without full and open competition, stating the legal basis for the exception.
A Justification and Approval (J&A) is the mandatory written document that federal agencies must prepare, approve at the appropriate authority level, and publish when awarding a contract without full and open competition, stating the specific statutory exception being invoked.
What is a Justification and Approval?
Under FAR 6.303, when an agency intends to use a non-competitive procurement, including a sole-source contract, it must prepare a J&A document before award. The J&A identifies:
- The agency and contracting activity
- The nature and description of the action being approved
- A description of the supplies or services to be contracted
- The statutory authority permitting the non-competitive action (one of seven CICA exceptions)
- Demonstration that the proposed contractor's unique qualifications or nature of the acquisition requires use of the authority
- A description of efforts made to ensure offers were solicited from as many potential sources as possible
- A determination that the anticipated cost is fair and reasonable
- A market research description
- Any other facts supporting the justification
- Signature of the contracting officer certifying the accuracy of the J&A
Approval authority depends on the contract value. For awards up to $750,000, the contracting officer may approve. Awards between $750,000 and $15 million require competition advocate approval. Awards between $15 million and $75 million require the head of the procuring activity. Awards above $75 million require the senior procurement executive. Above $100 million, the J&A must also be published on SAM.gov for 14 days before award.
Why J&As matter for government contractors
J&As are public documents for large awards, and they are a gold mine of competitive intelligence. A competitor who loses a non-competitive award can read the J&A on SAM.gov to understand why they were locked out. If the justification is legally insufficient, the J&A is the evidence needed to file a bid protest challenging the sole-source award. Monitoring J&As also reveals incumbent contractors and upcoming recompetes, when a sole-source extension is awarded, it often signals the agency will run a full competition when the extension expires.
Example
The Department of Energy awards a $25 million sole-source contract to a laboratory for specialized nuclear materials research, citing the "only one responsible source" exception. The contracting officer prepares a J&A documenting that only this lab has the specific hot cell facilities and licensed materials handlers required for the research. The J&A is approved by the head of the procuring activity and published on SAM.gov. A competing lab reviews the J&A, disagrees with the sole-source rationale, and files a GAO protest arguing that its own facilities are equivalent.
Frequently Asked Questions
Are all J&As publicly available?
J&As above $25,000 are generally publicly available. Those above $100 million are published on SAM.gov for a 14-day comment period before award. Classified contracts and contracts involving national security may have J&As withheld from public release.
Can the government issue a J&A for urgency?
Yes. The "unusual and compelling urgency" exception (FAR 6.302-2) allows non-competitive awards when delay would seriously damage the public interest. However, agencies cannot manufacture urgency through poor planning. A protest can challenge whether the urgency was genuine or created by the agency's own procurement failures.
What is the difference between a J&A and a Determination and Findings (D&F)?
Both are written approvals, but they cover different exceptions. A J&A covers exceptions to full and open competition under FAR Part 6. A Determination and Findings (D&F) covers other procurement exceptions, such as using a specific contract type or making determinations about contractor responsibility.
How long is a J&A valid?
Once approved and the contract is awarded, the J&A becomes part of the permanent contract file. If the agency wants to exercise options or make follow-on sole-source awards, a new J&A may be required depending on the circumstances and value.
How Bidovate helps
Bidovate puts Justification and Approval (J&A) to work inside your capture and proposal workflow.
Opportunity discoverySee Bidovate in action
Book a demo and we will show you the platform using your actual contract data.
Related terms
Sole Source Contract
A federal contract awarded without full and open competition because only one contractor can meet the need.
ViewFull and Open Competition
Full and open competition requires federal agencies to allow all responsible sources to submit bids or proposals on a contract, maximizing competitive pressure on price and quality.
ViewCompetition in Contracting Act (CICA)
CICA is the 1984 law that established full and open competition as the default requirement for federal procurement and created the automatic stay in bid protests at the GAO.